Project Time-Schedule

Project Plan - Voice over MPLS (2014)
Outcomes
March 2014
April 2014
May 2014
June 2014
July 2014
Aug 2014
Sep 2014
Oct 2014
Nov 2014
Total (Hrs)










1
Initial negotiation (i.e. understanding the problem and requirements). (Hrs.)
(20)
03/03 – 15/03








 20

Actual hours
15








15
2
Initial plan, budget & proposal submission (hrs.)
( 12)
17/03 – 28/03
(12 )
01/04 – 14/04







24

Actual hours
 12
12






24
3
Client meetings (hrs.)
4
4
4
4  
4  

30

Actual hours
2





2
4
MPLS/VoIP research, MPLS Lab
(48)
01/04 – 30/04






48

Actual hours







5
VoIP configuration tests, result analysis
(48)
01/05 – 31/05





48

Actual hours




6
MPLS configuration tests, result analysis progress report
(48)
01/06 – 30/06



48

Actual hours



7
Protocol integration research, lab simulation , result analysis




(48)
01/07 – 31/07




48

Actual hours







8
Network measurements, basic security implementation



(48)
01/08 – 31/08

48

Actual hours









10
Feature implementation, network capacity test, result analysis






(48)
01/09 – 31/09

48

Actual hours









11
Test results and analysis, Final report draft




(24)
01/09 (Start)
(24)
15/10 (End)

48

Actual hours










12
Final presentation, P&L/project Report submission







(48)
01/10 – 30/10

48
12
Total Budget Hours ()
36
62
52
52
52
52
76
76
(458)